Universal Containers (UC) is planning for a huge data migration as part of their Service Cloud Implementation. UC has approximately 15 million customers, 30 million contacts, and 30 million active cases.
Which two key areas of UC's data migration test plan should be included? (Choose two.)
Answer options
- A. APIs to be used for data migration
- B. Target Salesforce Server and Source system IP address
- C. Manual and Automated data validation approaches
- D. Success criteria for data migration
Correct answer: C, D
Explanation
The correct answers, C and D, focus on ensuring data integrity and defining what successful migration looks like, which are essential for a large-scale migration. Options A and B, while relevant to the migration process, do not directly relate to the testing aspect of the migration plan.