Salesforce Certified Development Lifecycle and Deployment Architect — Question 50
Universal Containers has defined a software tool to support agile processes, but the development team is not regularly updating the status of their work in progress.
Which Scrum value is compromised by this bad practice, and why?
Answer options
- A. Focus, because the teams are not focusing in the agile process expected activities.
- B. Courage, because the teams should be transparent about progress and speak up when they need help.
- C. Commitment, because the team is not committed to following the Agile methodology.
Correct answer: B
Explanation
The correct answer is B because transparency about progress is fundamental in Scrum, allowing teams to communicate openly and seek help when needed. A focuses on the team's concentration, which is less relevant to the issue of status updates, while C refers to adherence to methodology rather than the transparency aspect.