Salesforce Certified CPQ Specialist — Question 88

Universal Containers has a multi-layer bundle with a Percent of Total option in the first level. This Percent of Total option's calculation should be based on other options in the same level.
How should the Admin set this up?

Answer options

Correct answer: A

Explanation

The correct answer is A because setting the Percent of Total Scope field to Components ensures that the calculation includes only the associated options at the same level. Option B is incorrect as Group would consider a different grouping, while C and D do not address the specific requirement for the Percent of Total calculation at the specified level.