Pure Storage FlashArray Implementation Specialist — Question 32

A customer has purchased a DirectFlash Shelf, but lacks available space in the same rack as the chassis. There is available space in a rack 6m away. What step should be taken prior to implementation?

Answer options

Correct answer: B

Explanation

The correct answer is B, as longer cables are necessary to connect the DirectFlash Shelf located 6m away from the chassis. Option A does not address the lack of space, while option C would not be ideal since running longer cables is a more efficient solution.