PRINCE2 Re-Registration — Question 2
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.
Answer options
- A. the measurement of benefits NOT yet realized
- B. the handover of products
- C. open issues and risks
- D. the release of resources
Correct answer: C
Explanation
The correct answer, C, highlights the importance of addressing unresolved issues and risks before concluding a project. Options A and B focus on measuring benefits and product handover, which are not the primary concerns of the closing phase. Option D refers to resource release, which, while important, does not specifically relate to addressing ongoing project challenges.