PRINCE2 Practitioner — Question 49

The City Council needs to approve all funding requests for projects in the ‘Louistown is Open for Business’ portfolio. The project initiation documentation (PID) for LouisShopping has been prepared. As part of the ‘directing a project’ process, the project executive has passed the PID and full business case to the City Council for approval and requested the City Council to ‘authorize the project’ so that the design work on the regenerated shopping centre can start.
Is this an appropriate application of the ‘directing the project’ process, and why?

Answer options

Correct answer: A

Explanation

The correct answer is A, as it correctly identifies that the City Council's approval is essential for authorizing the design work as part of the funding process. Option B is incorrect because project authorization still needs to be communicated to the business areas. Option C is wrong because the PID approval is sufficient to commence design work, and option D is incorrect since the project manager's request for authorization is appropriate at this stage.