PRINCE2 Practitioner — Question 19

PROGRESS -
The project board has asked the project manager to produce highlight reports every two weeks during stage 4, as the project is near completion. The standard for the rest of the project was every four weeks.
Which statement explains why this is appropriate?

Answer options

Correct answer: A

Explanation

Option A is correct because it emphasizes that highlight reports must align with the project board's information requirements, especially as the project nears completion. Options B, C, and D do not directly address the specific needs of the project board regarding report frequency and content during this critical stage.