PRINCE2 Practitioner 6th Edition — Question 48

During stage 3, project costs are increasing but there will still be a positive return on investment, as documented in the business case. However, corporate management has recently revised its targets for return on investment and has decided to stop the project as it will not meet the new targets.
Is this an appropriate application of the 'continued business justification' principle?

Answer options

Correct answer: C

Explanation

The correct answer is C because the project's business case still indicates that it can provide a positive return, thus justifying its continuation despite rising costs. Options A and B incorrectly suggest that any change in corporate strategy or returns should automatically lead to project termination, while option D misinterprets the principle by stating that corporate strategy changes should not affect an authorized project.