PRINCE2 Practitioner 6th Edition — Question 44
The project is at the end of stage 4. The project manager has changed the benefits management approach. It now includes all the activities necessary to measure the increased revenue.
Who should approve this update?
Answer options
- A. Corporate management
- B. Project board
- C. Project assurance
- D. Project manager
Correct answer: B
Explanation
The Project Board is the correct authority to approve significant changes in the benefits management approach, as they are responsible for overseeing the project's direction and ensuring alignment with organizational objectives. Corporate management may have a broader oversight role but is not involved in day-to-day project decisions, while Project Assurance focuses on project compliance and quality rather than approvals. The Project Manager implements changes but does not have the authority to approve them.