PRINCE2 Practitioner 6th Edition — Question 23

The external team manager for the 'e-learning course' has reviewed the quality register to ensure all quality activities have been completed. The 'e-learning course' has been approved and accreditation has been achieved. As a result, the team manager updated the work package to notify the project manager that it is complete, and updated the team plan.
Is this appropriate, and why?

Answer options

Correct answer: A

Explanation

The correct answer is A because the project manager must be informed that all activities have been completed and approved. Option B is incorrect as a team plan is not a requirement for the work package in this context. Options C and D are also wrong since they misinterpret the necessary actions regarding project documentation.