PRINCE2 Practitioner 6th Edition — Question 23
The external team manager for the 'e-learning course' has reviewed the quality register to ensure all quality activities have been completed. The 'e-learning course' has been approved and accreditation has been achieved. As a result, the team manager updated the work package to notify the project manager that it is complete, and updated the team plan.
Is this appropriate, and why?
Answer options
- A. Yes, because the project manager needs to receive confirmation that work has been completed and approved.
- B. Yes, because a team plan to gain accreditation of the 'e-learning course' is required to be part of the work package.
- C. No, because it is the configuration item record of the relevant product description that is updated, not the work package.
- D. No, because the work package should be checked to confirm the reporting arrangements of the 'e-learning course'.
Correct answer: A
Explanation
The correct answer is A because the project manager must be informed that all activities have been completed and approved. Option B is incorrect as a team plan is not a requirement for the work package in this context. Options C and D are also wrong since they misinterpret the necessary actions regarding project documentation.