PRINCE2 Foundation — Question 90
What is the definition of a project outcome?
Answer options
- A. A measurable improvement that is perceived as an advantage by one or more stakeholders
- B. The reason for the project
- C. The result of the change derived from using the project's outputs
- D. The project's specialist products.
Correct answer: C
Explanation
The correct answer, C, accurately describes a project outcome as it highlights the result of changes that occur from the outputs generated by the project. Options A, B, and D focus on other aspects of a project rather than the specific result of changes attributed to outputs, making them incorrect in this context.