PRINCE2 Foundation — Question 87
When might the 'controlling a stage' process be used?
Answer options
- A. During the 'closing a project' process
- B. During the 'directing a project' process
- C. During the 'initiating a project' process
- D. During the 'starting a project' process
Correct answer: A
Explanation
The 'controlling a stage' process is utilized during the 'closing a project' process to ensure that all project deliverables are completed and validated. The other options relate to different phases of the project lifecycle where controlling is not the primary focus, making them incorrect in this context.