PRINCE2 Foundation — Question 83

Which product defines how the project board should approve the management products produced during the 'initiating a project' process?

Answer options

Correct answer: B

Explanation

The Quality management approach is the correct answer because it details the standards and criteria for approval of management products. The Communication management approach focuses on stakeholder communication, the Project plan encompasses the overall project strategy, and the Initiation stage plan relates to the initial phase activities rather than specifically addressing approval criteria.