PRINCE2 Foundation — Question 80
Why are projects divided into management stages?
Answer options
- A. To ensure the justification for the project is recorded and approved
- B. To help the project board to assess a project's ongoing viability
- C. To delegate authority for delivering the products to the team manager
- D. To focus on the delivery of products to defined quality requirements
Correct answer: B
Explanation
The correct answer, B, highlights the importance of evaluating a project's ongoing viability, which is crucial for effective project management. While A, C, and D address important aspects of project management, they do not specifically relate to the continuous assessment of viability, which is the primary purpose of dividing projects into stages.