PRINCE2 Foundation — Question 75
Which is a factor when deciding the duration of a management stage?
Answer options
- A. The work packages to be delivered
- B. The level of risk in the project
- C. The cost of the stage
- D. The number of products to be produced in the project
Correct answer: B
Explanation
The correct answer is B, as the level of risk influences the duration of a management stage due to the need for more time in risk assessment and mitigation. The other options, while relevant to project management, do not directly affect the duration of the management stage in the same way that risk does.