PRINCE2 Foundation — Question 70
Which is an objective of the Closing a Project process?
Answer options
- A. Prepare the plan for the next stage
- B. Assess any benefits that have already been realized
- C. Produce a Benefits Review Plan to identify what benefits are expected
- D. Check that all benefits are realized before closing a project
Correct answer: B
Explanation
The correct answer is B because the Closing a Project process involves evaluating the benefits that have been realized during the project. Options A, C, and D do not align with the primary objectives of this process, as they focus on planning future stages or benefits that are not yet realized.