PRINCE2 Foundation — Question 65
Which is a type of issue?
Answer options
- A. A lesson
- B. A request for change
- C. An Exception Report
- D. A risk with an estimated high impact
Correct answer: B
Explanation
The correct answer is B, as a request for change is a recognized type of issue within project management. Options A, C, and D do not classify as issues but rather represent different aspects of project documentation or risk management.