PRINCE2 Foundation — Question 62

Which does NOT reflect the PRINCE2 principle of continued business justification?

Answer options

Correct answer: C

Explanation

Option C is correct because it suggests halting a project based solely on financial forecasts, which is not explicitly part of the principle of continued business justification. The other options (A, B, D) all emphasize the importance of maintaining a valid reason for the project throughout its lifecycle, aligning with PRINCE2 principles.