PRINCE2 Foundation — Question 53

Which is a key decision made during the 'directing a project' process?

Answer options

Correct answer: C

Explanation

The correct answer is C because confirming that the benefits management approach addresses all expected benefits is crucial for ensuring the project delivers value. The other options, while important, do not specifically relate to the overall benefits management, which is central to directing the project.