PRINCE2 Foundation — Question 53
Which is a key decision made during the 'directing a project' process?
Answer options
- A. Select and appoint the project executive
- B. Approve the project manager role description
- C. Confirm that the benefits management approach addresses all expected benefits
- D. Approve the proposed project mandate
Correct answer: C
Explanation
The correct answer is C because confirming that the benefits management approach addresses all expected benefits is crucial for ensuring the project delivers value. The other options, while important, do not specifically relate to the overall benefits management, which is central to directing the project.