PRINCE2 Foundation — Question 5

Which product records any project outcomes perceived as negative by stakeholders?

Answer options

Correct answer: A

Explanation

The Business Case is designed to document the rationale for a project, including any negative outcomes perceived by stakeholders. The Project Plan focuses on how the project will be executed and managed, while the Communication Management Strategy outlines communication processes. The Project Product Description details the deliverables and their acceptance criteria, but does not specifically address stakeholder perceptions of outcomes.