PRINCE2 Foundation — Question 40
Which is a minimum requirement for applying the plans theme?
Answer options
- A. The project must have at least two management stages
- B. The team managers in the project must prepare team plans
- C. Scope tolerance must be prioritized using MoSCoW
- D. The project plan must be presented as a Gantt chart
Correct answer: A
Explanation
The correct answer is A because having at least two management stages is essential for applying the plans theme, which ensures structured project management. Options B, C, and D are not minimum requirements; they pertain to specific planning activities or formats that may enhance project management but are not foundational for applying the plans theme.