PRINCE2 Foundation — Question 38

Which process is used to define how baselines will be established and controlled?

Answer options

Correct answer: C

Explanation

The correct answer is C, as the Initiating a project process includes defining the project's objectives and establishing baselines. Options A, B, and D do not focus on the establishment of baselines; instead, they pertain to managing project stages, directing overall project efforts, and the commencement of the project, respectively.