PRINCE2 Foundation — Question 38
Which process is used to define how baselines will be established and controlled?
Answer options
- A. Controlling a stage
- B. Directing a project
- C. Initiating a project
- D. Starting up a project
Correct answer: C
Explanation
The correct answer is C, as the Initiating a project process includes defining the project's objectives and establishing baselines. Options A, B, and D do not focus on the establishment of baselines; instead, they pertain to managing project stages, directing overall project efforts, and the commencement of the project, respectively.