Why can PRINCE2 be applied to any type of project?
Answer options
- A. Because it provides the project manager with procedures for managing project risks and issues
- B. Because it allows each member of the project management team to fully understand their role and responsibilities
- C. Because it separates the management of the project from the specialist work needed to deliver the products
- D. Because it provides the project manager with a planning procedure to plan the project more effectively
Correct answer: C
Explanation
The correct answer is C because PRINCE2's framework is designed to separate project management from the specific tasks involved in delivering products, making it adaptable to any project type. Options A, B, and D, while beneficial, do not address the fundamental reason for the methodology's applicability across various projects.