PRINCE2 Foundation — Question 343

Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

Answer options

Correct answer: C

Explanation

Statement 1 is correct because the Project Initiation Documentation is essential for establishing a solid foundation before project approval. Statement 2 is also true, as the documentation should be revised after each stage to ensure it reflects the project's current status, making the correct answer C.