PRINCE2 Foundation — Question 343
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
Answer options
- A. Only 1 is true
- B. Only 2 is true
- C. Both 1 and 2 are true
- D. Neither 1 or 2 are true
Correct answer: C
Explanation
Statement 1 is correct because the Project Initiation Documentation is essential for establishing a solid foundation before project approval. Statement 2 is also true, as the documentation should be revised after each stage to ensure it reflects the project's current status, making the correct answer C.