PRINCE2 Foundation — Question 340
Which is NOT considered when defining risk tolerance?
Answer options
- A. A Project Board's attitude towards risk taking
- B. The allocated risk budget
- C. An organization's risk appetite
- D. The amount of risk a Project Board considers acceptable
Correct answer: B
Explanation
The correct answer is B because the allocated risk budget is a financial consideration rather than a measure of risk tolerance. Options A, C, and D all pertain to attitudes and acceptability regarding risk, which are crucial elements in defining risk tolerance.