PRINCE2 Foundation — Question 337

The project manager needs to record the impact assessment for a specific business opportunity.

In which management product should the project manager record this?

Answer options

Correct answer: C

Explanation

The correct answer is C, the Risk register, as it is specifically designed to document potential risks and their impact assessments related to business opportunities. The other options, such as Issue report and Issue register, are more focused on problems that have already occurred, while the Quality register is used to track quality-related metrics, not risks.