What is likely to be avoided by applying the ‘tailor to suit the project’ principle?

Answer options

Correct answer: D

Explanation

The 'tailor to suit the project' principle aims to streamline processes and reduce inefficiencies, which helps in avoiding unnecessary management effort. Options A, B, and C are important considerations but are not directly addressed by this principle, as travel costs, project complexity, and team skills may still vary regardless of how the project is tailored.