PRINCE2 Foundation — Question 303
The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual products being worked on.
Which part of effective issue management is the project manager applying?
Answer options
- A. Baselines
- B. Change budget
- C. Change control
- D. Issue resolution
Correct answer: A
Explanation
The correct answer is A, as baselines provide a reference point to compare the planned and actual performance of a project. The other options focus on different aspects of project management; for instance, change budget pertains to financial adjustments, change control involves managing changes to the project scope, and issue resolution deals with addressing problems as they arise.