PRINCE2 Foundation — Question 29
Where should decisions regarding the tailoring of the project be recorded?
Answer options
- A. Project brief
- B. Project initiation documentation
- C. Project mandate
- D. Stage plan
Correct answer: B
Explanation
The correct answer is B, as the Project initiation documentation is specifically designed to capture decisions made about the project, including tailoring aspects. The other options, such as the Project brief and Project mandate, do not serve the primary purpose of detailing project customization decisions, while the Stage plan focuses more on the execution phases rather than initial tailoring.