PRINCE2 Foundation — Question 280
Identify the missing words in the following sentence.
The ‘starting up a project’ process is triggered when a [?] is available.
Answer options
- A. project business case
- B. project mandate
- C. stage plan
- D. work package
Correct answer: B
Explanation
The correct answer is 'project mandate' because it formally authorizes the project to begin. The project business case outlines the justification for the project but does not trigger the process. The stage plan and work package are related to project execution, not initiation.