PRINCE2 Foundation — Question 276
Which describes a time-driven control?
Answer options
- A. The dates for the project’s end stage assessment included in the project plan
- B. The expected frequency of progress reports specified in a work package
- C. The expected dates for planned checks of specialist products included in a stage plan
- D. The planned exception assessment meeting to authorize a requested exception plan
Correct answer: B
Explanation
The correct answer is B because it specifies the regularity with which progress reports are expected, highlighting a time-based control. Options A, C, and D, while related to project timing, do not focus specifically on the frequency of reporting, which is essential for time-driven controls.