PRINCE2 Foundation — Question 27
When should the level of tailoring be defined?
Answer options
- A. During the initiation stage
- B. When reviewing what has been learned to date
- C. As a response to issues and risks experienced
- D. Before the project is triggered by the project mandate
Correct answer: A
Explanation
The correct answer is A, as defining the level of tailoring occurs during the initiation stage when the project is being set up. Options B, C, and D refer to times when adjustments may be necessary, but they do not represent the initial establishment of tailoring guidelines.