PRINCE2 Foundation — Question 260
Which describes a project benefit?
Answer options
- A. A specialist product of the project
- B. The result of a change derived from using the project's products
- C. An uncertain result caused by project actions
- D. A measurable improvement resulting from an outcome
Correct answer: D
Explanation
The correct answer, D, accurately defines a project benefit as a measurable improvement that arises from the project's results. Options A and B describe aspects related to the project but do not capture the essence of a benefit. Option C incorrectly portrays project benefits as uncertain results, which is not aligned with the definition.