PRINCE2 Foundation — Question 258
Which is a minimum requirement for applying the risk theme?
Answer options
- A. Threats must be assessed for their impact on the viability of the project
- B. A single role that is responsible for all risks must be defined
- C. The PRINCE2 risk management procedure must be followed
- D. Team managers must maintain their own risk registers
Correct answer: A
Explanation
Assessing threats for their impact on the project's viability is essential, as it helps identify potential risks that could jeopardize the project. The other options may support risk management efforts, but they are not minimum requirements; for instance, defining a single role or having team managers maintain registers can enhance the process but are not strictly necessary.