According to the minimum requirements for the plans theme, which type of plan is optional?
Answer options
- A. Project plan
- B. Stage plan
- C. Exception plan
- D. Team plan
Correct answer: D
Explanation
The Team plan is considered optional because it is not essential for the overall project management framework, while the Project plan, Stage plan, and Exception plan are all necessary components. These required plans support the structured approach needed to manage the project effectively.