PRINCE2 Foundation — Question 241
What should the project manager do to support the 'learn from experience' principle?
Answer options
- A. Incorporate lessons identified into the regular checkpoint report
- B. Seek supplier experiences when considering the project approach
- C. Summarize project lessons in a lessons log during project closure
- D. Produce the executive's role description and responsibilities
Correct answer: B
Explanation
The correct answer is B because seeking supplier experiences can provide valuable insights that contribute to the project's approach and improve future outcomes. Options A and C focus on documenting lessons rather than actively gathering insights, while D is unrelated to the learning process.