PRINCE2 Foundation — Question 239

Which is a purpose of the ‘controlling a stage’ process?

Answer options

Correct answer: C

Explanation

The correct answer is C because the 'controlling a stage' process involves producing regular highlight reports to keep the project board informed about progress. Option A is incorrect as it pertains to project closure, not stage control. Option B relates to work package management but does not capture the essence of stage control, and option D refers to re-planning which is a separate process from controlling a stage.