PRINCE2 Foundation — Question 237
Which is a minimum requirement for applying the ‘change’ theme?
Answer options
- A. Specify in the change control approach the means by which project products will be protected
- B. Document the format and contents of the issue register
- C. Produce issue reports to document the impact assessment for requests for change
- D. Delegate the change authority to the senior supplier(s) for supplier off-specifications
Correct answer: B
Explanation
The correct answer is B because documenting the format and contents of the issue register is fundamental for managing issues effectively. Options A, C, and D, while important, do not represent minimum requirements for applying the 'change' theme specifically.