PRINCE2 Foundation — Question 214
Which describes a risk event?
Answer options
- A. The area of uncertainty in terms of the threat or opportunity
- B. The derivation or sources of a potential risk to the project
- C. The achievement of a milestone on the project plan
- D. The sequence of events and actions that will be put in place if a risk occurs
Correct answer: A
Explanation
The correct answer, A, identifies a risk event as the uncertainty surrounding potential threats or opportunities, which is fundamental in risk management. Option B refers to the origins of risks rather than defining an event, C pertains to project milestones unrelated to risk, and D describes a response strategy rather than the risk event itself.