PRINCE2 Foundation — Question 210
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
Answer options
- A. End Stage Report
- B. Team Plan
- C. Work Package
- D. Project Plan
Correct answer: D
Explanation
The correct answer is D, Project Plan, as it is the document that encompasses the overall project schedule and budget, which need to be updated before the new stage begins. The End Stage Report (A) summarizes the previous stage, the Team Plan (B) focuses on team tasks, and the Work Package (C) details specific deliverables, none of which are updated with estimates for the new stage.