PRINCE2 Foundation — Question 206

Which role is responsible for ensuring the project is justified in terms of cost?

Answer options

Correct answer: B

Explanation

The Executive is responsible for ensuring that the project has a valid business justification, including cost considerations. The Project Manager focuses on the day-to-day management of the project, while the Senior User and Senior Supplier roles deal with user requirements and supplier inputs, respectively, rather than overall project justification.