Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
Answer options
- A. Project Brief
- B. Project Initiation Documentation
- C. Project mandate
- D. Benefits Review Plan
Correct answer: B
Explanation
The correct answer is B, Project Initiation Documentation, as it serves as the key reference point for the Project Board to monitor and assess the project's status. The other options, while related to project management, do not provide the comprehensive framework needed for ongoing assessments.