PRINCE2 Foundation — Question 179

Which is a minimum requirement for applying the 'progress' theme?

Answer options

Correct answer: C

Explanation

'To manage by exception against tolerances set for time and cost' is correct because it ensures that the project remains on track by focusing on significant deviations. The other options, while important to project management, do not specifically address the requirements for applying the 'progress' theme.