Which is a minimum requirement for applying the 'progress' theme?
Answer options
- A. To ensure progress towards the outcome remains consistent
- B. To maintain the project's registers and logs
- C. To manage by exception against tolerances set for time and cost
- D. To produce highlight and end stage reports
Correct answer: C
Explanation
'To manage by exception against tolerances set for time and cost' is correct because it ensures that the project remains on track by focusing on significant deviations. The other options, while important to project management, do not specifically address the requirements for applying the 'progress' theme.