PRINCE2 Foundation — Question 177

What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products

Answer options

Correct answer: B

Explanation

The correct answer is B because 'controlling a stage' involves authorizing work to be executed and taking corrective measures when necessary. Options A, C, and D include actions that do not directly pertain to the controlling process, such as creating exception plans and obtaining approvals for completed products.