PRINCE2 Foundation — Question 175
Which is a true statement about time-driven controls?
Answer options
- A. Time-driven controls are used for monitoring the progress of Work Packages and management stages
- B. Time-driven controls take place when specific events happen
- C. Time-driven controls are produced at the end of a stage
- D. An Exception Report is a time-driven control
Correct answer: A
Explanation
The correct answer is A because time-driven controls are specifically designed to monitor the progress of Work Packages and management stages throughout a project. Options B, C, and D are incorrect as they describe other types of controls or events that do not align with the definition of time-driven controls.