PRINCE2 Foundation — Question 171
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
Answer options
- A. Controlling a Stage
- B. Closing a Project
- C. Directing a Project
- D. Managing a Stage Boundary
Correct answer: D
Explanation
The correct answer, Managing a Stage Boundary, is the process that allows the Project Board to evaluate the outcomes of a completed stage and decide if the project should proceed. Controlling a Stage focuses on managing the current stage, Closing a Project deals with project completion, and Directing a Project relates to overall governance rather than stage-specific assessments.