PRINCE2 Foundation — Question 17

Which product describes the method the project will use to engage with corporate, programme management or the customer?

Answer options

Correct answer: B

Explanation

The correct answer is B, as the communication management approach specifically outlines how information will be shared among stakeholders. Options A, C, and D focus on different aspects of project management, such as maintaining quality, managing changes, and realizing benefits, but do not address the engagement strategy directly.