PRINCE2 Foundation — Question 168
Which is a purpose of the Risk theme?
Answer options
- A. Establish a method for the implementation of continuous improvement during the project
- B. Identify, assess and control problems that have occurred
- C. Provide the Project Board with a time-driven control to capture all project risks
- D. Establish a cost-effective procedure to identify, assess and control risks
Correct answer: D
Explanation
The correct answer is D because the Risk theme focuses on establishing a cost-effective procedure to manage risks throughout the project. Options A, B, and C do not accurately reflect the primary aim of the Risk theme, as they pertain to continuous improvement, problem management, and time-driven controls rather than specifically addressing risk management.