PRINCE2 Foundation — Question 158
What should be included in the PID as a minimum requirement for managing organization?
Answer options
- A. Definition of the training required throughout the project
- B. Documentation of the project management team structure
- C. An analysis of the power and influence of the major stakeholders
- D. A description of the customer's quality expectations
Correct answer: B
Explanation
The correct answer is B because the PID must document the structure of the project management team to ensure clarity in roles and responsibilities. Options A, C, and D, while important, are not minimum requirements for the PID and do not directly pertain to the management structure.