PRINCE2 Foundation — Question 156
What is the first task of product-based planning?
Answer options
- A. Produce the Initiation Stage Plan
- B. Write the Project Product Description
- C. Identify dependencies
- D. Create the product breakdown structure
Correct answer: B
Explanation
The correct answer is B because the first task in product-based planning is to create a clear Project Product Description, which outlines what the product is intended to deliver. The other options, while important, occur later in the planning process; producing the Initiation Stage Plan (A), identifying dependencies (C), and creating the product breakdown structure (D) are all dependent on having a defined product description.